Project Completion Certificate (Ground Water)
Scheme ID: 20059714 Name of Scheme: SINGOHA (GOGP) JJM No. of Villages: 2 No. of Habitation Covered: 7
Total Population Covered: 6080 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 26-Jul-2024 Actual Date of Completion (Capex): 27-Apr-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 37M / 113M SINGOHA 27.647857 80.052448
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 76.8M³ / 45M SINGOHA 27.647857 80.052448
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 375KL / 16M SINGOHA 27.647857 80.052448
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE 200 0.032
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN:-6 63 5.308
2 HDPE PIPE PN:-6 75 4.521
3 HDPE PIPE PN:-6 90 4.131
4 HDPE PIPE PN:-6 110 2.465
5 HDPE PIPE PN:-6 125 0.555
6 HDPE PIPE PN:-6 140 1.144
7 HDPE PIPE PN:-6 160 0.459
8 HDPE PIPE PN:-6 180 0.195
9 HDPE PIPE PN:-6 200 0.043
HSC Connection
Sno. Total Nos.
1 1173
Other Details
3.77
0.00
3.75
26-Jul-2025
30-Sep-2025