Project Completion Certificate (Ground Water)
Scheme ID: 20059467 Name of Scheme: KUSAILA VILLAGE WATER SUPPLY SCHEME No. of Villages: 3 No. of Habitation Covered: 5
Total Population Covered: 3834 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 16-Dec-2023 Actual Date of Completion (Capex): 31-Dec-2026
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 200 21 m/65.31 m Kusaila 25.662326 82.939627
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 12.5 HP 800LPM/44 M Kusaila 25.662326 82.939627
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 225 KL/12 M Kusaila 25.3943 82.5623
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI_K-7 150 0.0213 yes
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 90 .818 yes
2 HDPE 75 4.152 yes
3 HDPE 63 10.885 yes
4 HDPE 110 1.256 yes
5 HDPE 125 .691 yes
6 HDPE 140 1.314 yes
7 HDPE 160 .628 yes
8 HDPE 180 1.397 yes
9 HDPE 200 .558 yes
HSC Connection
Sno. Total Nos.
1 436
Other Details
3.02
3.02
2.62
25-Feb-2025
26-Feb-2025