Project Completion Certificate (Ground Water)
Scheme ID: 20058315 Name of Scheme: NAGLA LOTHU (GOGP) JJM No. of Villages: 3 No. of Habitation Covered: 3
Total Population Covered: 6050 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 26-Jul-2024 Actual Date of Completion (Capex): 02-May-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 27M / 99M NAGLA LOTHU 27.592872 79.95254
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 72.6 M³ / 41M NAGLA LOTHU 27.592872 79.95254
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 350KL / 12M NAGLA LOTHU 27.592872 79.95254
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE 200 0.41
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN:-6 63 4.16
2 HDPE PIPE PN:-6 75 2.811
3 HDPE PIPE PN:-6 90 2.069
4 HDPE PIPE PN:-6 110 0.911
5 HDPE PIPE PN:-6 125 0.245
6 HDPE PIPE PN:-6 140 0.552
7 HDPE PIPE PN:-6 160 0.477
8 HDPE PIPE PN:-6 180 0.00
9 HDPE PIPE PN:-6 200 0.927
HSC Connection
Sno. Total Nos.
1 1215
Other Details
3.31
0.00
3.38
01-Aug-2025
30-Sep-2025