Project Completion Certificate (Ground Water)
Scheme ID: 20050775 Name of Scheme: BANUADEEH VILLAGE WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 9
Total Population Covered: 3125 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 30-Dec-2026 Actual Date of Completion (Capex): 30-Jun-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 300 12m/53.05m Banuadeeh 26.02185 82.616975
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 12.5 HP 660 LPM/47 M Banuadeeh 26.02185 82.616975
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 200 KL/16 Mtr Banuadeeh 26.021674 82.616717
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-7 150 0.0255 Yes
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 90 1.73 yes
2 HDPE 75 2.54 yes
3 HDPE 63 2.88 yes
4 HDPE 110 1.04 yes
5 HDPE 140 0.504 yes
6 HDPE 160 0.821 yes
7 HDPE 180 1.269 yes
HSC Connection
Sno. Total Nos.
1 342
Other Details
2.29
2.29
2.00
30-Jun-2025
30-Jun-2025