Project Completion Certificate (Ground Water)
Scheme ID: 20048074 Name of Scheme: HUSAINPUR MAJRA MANAKJUDI AND UMAR MOHHAMADPUR MULTIVILLAGE WATER SUPPLY SCEME(O) No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 2374 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 10-May-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 18.03/102.53 HuSainpur Majara Manakjudi 28.889704 78.562336
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Solar Powered Pump 510/39 Husainpur Majra Manakjudi 28.889704 78.562336
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Cast in situ Zinc Zincalume 150/12 Husainpur Majra Manakjudi 28.88961999 78.56243833
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 K-7/DI 125 0.04845
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 PN-6 PE100/HDPE 90 0.9914
2 PN-6 PE100/HDPE 75 0.391
3 PN-6 PE100/HDPE 63 4.7611
4 PN-6 PE100/HDPE 110 0.2332
5 PN-6 PE100/HDPE 125 0.2197
6 PN-6 PE100/HDPE 140 0.1057
7 PN-6 PE100/HDPE 160 0.0225
HSC Connection
Sno. Total Nos.
1 451
Other Details
1.73
0.00
1.73
24-Aug-2025
25-Aug-2025