| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20047651 | Name of Scheme: KHUDA MOHAMMAD GARH Water Supply Scheme | No. of Villages: 1 | No. of Habitation Covered: 7 |
| Total Population Covered: 4270 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 23-Nov-2023 | Actual Date of Completion (Capex): 18-Jan-2026 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Lowering of tubewell assembly | 30/119.8 | khuda mohammadgarh | 26.282826 | 82.541094 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | AC Submersible Pump 17.5 hP | 900/46 | khuda mohammadgarh | 26.2828 | 82.5410 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | RCC | 250/16 | khuda mohammadgarh | 26.2828 | 82.5410 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | Dia K-7 | 150 | 0.040 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | PIPE PN-6 : Class PE-100 | 63 | 15511.64 | |
| 2 | PIPE PN-6 : Class PE-100 | 75 | 357.50 | |
| 3 | PIPE PN-6 : Class PE-100 | 90 | 753.70 | |
| 4 | PIPE PN-6 : Class PE-100 | 110 | 1982.00 | |
| 5 | PIPE PN-6 : Class PE-100 | 140 | 449.60 | |
| 6 | PIPE PN-6 : Class PE-100 | 160 | 1143.40 | |
| 7 | PIPE PN-6 : Class PE-100 | 200 | 1167.20 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 473 |