Project Completion Certificate (Ground Water)
Scheme ID: 20044301 Name of Scheme: Sarai Langar No. of Villages: 1 No. of Habitation Covered: 3
Total Population Covered: 2760 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 27-Nov-2023 Actual Date of Completion (Capex): 15-Mar-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube well 23/118 Sarai Langer 26.106592 80.394384
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submerssible Pump 580/55 Sarai Langer 26.106592 80.394384
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 175/16 Sarai Langer 26.106592 80.394384
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE K-7 100 0.04
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 8798.3
2 HDPE 75 2979.49
3 HDPE 90 2630
4 HDPE 110 763
5 HDPE 140 523
HSC Connection
Sno. Total Nos.
1 609
Other Details
3.06
0.00
3.05
05-Aug-2025
06-Aug-2025