Project Completion Certificate (Ground Water)
Scheme ID: 20034256 Name of Scheme: BAIJAPUR VILLAGE WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 11
Total Population Covered: 2575 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 18-Nov-2023 Actual Date of Completion (Capex): 12-Oct-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 300 6.1/55.02 Baijapur 25.826911 82.591596
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 10HP 503/44 Baijapur 25.826911 82.591596
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 150KL/12M Baijapur 25.826805 82.591117
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 K-7 100 0.0133 Yes
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 PN-6 90 1.272 Yes
2 PN-6 75 1.367 Yes
3 PN-6 63 3.676 Yes
4 PN-6 110 0.848 Yes
5 PN-6 140 0.824 Yes
6 PN-6 160 0.295 Yes
HSC Connection
Sno. Total Nos.
1 256
Other Details
2.19
2.19
1.61
12-Oct-2025
12-Oct-2025