Project Completion Certificate (Ground Water)
Scheme ID: 20033834 Name of Scheme: SASAPANA WATER SUPPLY SCHEME No. of Villages: 2 No. of Habitation Covered: 12
Total Population Covered: 7340 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 21-Oct-2023 Actual Date of Completion (Capex): 10-May-2026
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Lowering & Tubewell assembly 21.36/87.32 SASPANA 26.332237 82.522812
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 AC Submmercible Pumping plant 1450/46 SASPANA 26.33 82.522
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 RCC STRUCTURE 425/16 SASPANA 26.332 82.52
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI Pipe K-7 200 0.032
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 90 1.150
2 HDPE Pipe PN-6: Class PE-100 75 0.370
3 HDPE Pipe PN-6: Class PE-100 63 36.450
4 HDPE Pipe PN-6: Class PE-100 110 3.070
5 HDPE Pipe PN-6: Class PE-100 140 3.483
6 HDPE Pipe PN-6: Class PE-100 160 0.901
7 HDPE Pipe PN-6: Class PE-100 200 0.672
HSC Connection
Sno. Total Nos.
1 1011
Other Details
5.32
5.32
5.32
10-May-2026
12-May-2026