Project Completion Certificate (Ground Water)
Scheme ID: 20026125 Name of Scheme: FULWARI WATER SUPPLY SCHEME No. of Villages: 3 No. of Habitation Covered: 9
Total Population Covered: 3420 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 28-Sep-2023 Actual Date of Completion (Capex): 21-Sep-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube well 24.12 /55.74 FULWARI 26º 19' 44.258" N 82º 49' 58.088" E
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VTPump 45/46 FULWARI 26º 19' 44.258" N 82º 49' 58.088" E
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 RCC-Zink Alum Tank 200/16 FULWARI 26º 19' 44.258" N 82º 49' 58.088" E
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI Pipe K-7 150 0.035
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 63 15.356
2 HDPE Pipe PN-6: Class PE-100 75 2.93
3 HDPE Pipe PN-6: Class PE-100 90 0.694
4 HDPE Pipe PN-6: Class PE-100 110 0.577
5 HDPE Pipe PN-6: Class PE-100 140 2.116
6 HDPE Pipe PN-6: Class PE-100 160 0.0661
7 HDPE Pipe PN-6: Class PE-100 200 0.514
HSC Connection
Sno. Total Nos.
1 430
Other Details
2.85
0.00
2.81
03-Jan-2026
04-Jan-2026