| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20025556 | Name of Scheme: Ahrauli Ghat | No. of Villages: 1 | No. of Habitation Covered: 2 |
| Total Population Covered: 1980 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 25-Aug-2022 | Actual Date of Completion (Capex): 31-Dec-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tube well | 21/160.45 | Ahrauli Ghat | 26.108935 | 79.912817 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 42.19/71 | Ahrauli Ghat | 26.108935 | 79.912817 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 125/16 | Ahrauli Ghat | 26.108935 | 79.912817 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 100 | 0.025 | As per Site |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 2.578 | As per Site |
| 2 | HDPE | 75 | 0.068 | As per Site |
| 3 | HDPE | 110 | 0.960 | As per Site |
| 4 | HDPE | 140 | 0.359 | As per Site |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 301 |