Project Completion Certificate (Ground Water)
Scheme ID: 20025495 Name of Scheme: Chirkhiri No. of Villages: 1 No. of Habitation Covered: 6
Total Population Covered: 2675 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 25-Aug-2022 Actual Date of Completion (Capex): 31-Dec-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube well 24/142.02 Chirkiri 26.56109 79.692652
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 29.60/61 Chirkiri 26.56109 79.692652
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 175/16 Chirkiri 26.56109 79.692652
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 2.162 As per Site
2 HDPE 75 1.290 As per Site
3 HDPE 90 1.659 As per Site
4 HDPE 110 0.880 As per Site
5 HDPE 140 0.833 As per Site
6 HDPE 160 0.708 As per Site
7 HDPE 180 0.166 As per Site
HSC Connection
Sno. Total Nos.
1 486
Other Details
2.10
2.20
2.20
31-Aug-2023
01-Sep-2023