| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20024374 | Name of Scheme: Bamhanauti | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 1900 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 24-Aug-2023 | Actual Date of Completion (Capex): 31-Dec-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tube well | 24.02/128.53 | Bamhanuti | 26.29777 | 79.852373 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 39.10/62 | Bamhanuti | 26.29777 | 79.852373 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 100/12 | Bamhanuti | 26.29777 | 79.852373 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 100 | 0.019 | As per Site |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 4.666 | As per Site |
| 2 | HDPE | 75 | 0.533 | As per Site |
| 3 | HDPE | 90 | 0.526 | As per Site |
| 4 | HDPE | 110 | 0.261 | As per Site |
| 5 | HDPE | 140 | 0.416 | As per Site |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 404 |