Project Completion Certificate (Ground Water)
Scheme ID: 20023982 Name of Scheme: IZILPUR GRAMIN PEYJAL YOJNA No. of Villages: 1 No. of Habitation Covered: 2
Total Population Covered: 2270 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 06-Jul-2023 Actual Date of Completion (Capex): 15-Jan-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Plain Pipe 150mm Dia 24.12 Izilpur 27.044462 79.460489
2 Plain Pipe 200mm Dia 57.5 Izilpur 27.044462 79.460489
3 Slotted Pipe 150mm Dia 15 Izilpur 27.044462 79.460489
4 Slotted Pipe 200mm Dia 3 Izilpur 27.044462 79.460489
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 495/58 Izilpur 27.044462 79.460489
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Zn-Al Tank 150/12 Izilpur 27.044462 79.460489
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI Pipe 100 0.0128
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 Distribution Pipe/HDPE 63 3.227
2 Distribution Pipe/HDPE 75 0.757
3 Distribution Pipe/HDPE 90 0.341
4 Distribution Pipe/HDPE 110 0.218
5 Distribution Pipe/HDPE 125 0.076
6 Distribution Pipe/HDPE 160 0.151
7 Distribution Pipe/HDPE 180 1.306
HSC Connection
Sno. Total Nos.
1 402
Other Details
2.23
2.35
0.00
18-May-2025
01-Jan-2026