Project Completion Certificate (Ground Water)
Scheme ID: 20020270 Name of Scheme: CHAKKAN MOHAMMAD No. of Villages: 3 No. of Habitation Covered: 3
Total Population Covered: 3550 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 04-May-2024 Actual Date of Completion (Capex): 22-Jul-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 24/114.84 Chakkan Mohammad 26.5911 83.4513
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 48/42 Chakkan Mohammad 26.5911 83.4513
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Overhead Tank-1 250/14 Chakkan Mohammad 26.5911 83.4513
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 0.008 Laying Completed
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 8.8 Laying Completed
2 HDPE 75 0.513 Laying Completed
3 HDPE 90 0.318 Laying Completed
4 HDPE 110 0.196 Laying Completed
5 HDPE 140 1.328 Laying Completed
HSC Connection
Sno. Total Nos.
1 507
Other Details
2.53
0.00
2.42
21-Jul-2024
19-Nov-2025