Project Completion Certificate (Ground Water)
Scheme ID: 20018319 Name of Scheme: Baldiya Water Supply Scheme No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 4151 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 30-Jun-2025 Actual Date of Completion (Capex): 01-Oct-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 K-7 DI PIPE 150 0.03
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN -6: CLASS PE -100 63 7.64
2 HDPE PIPE PN -6: CLASS PE -100 75 0.89
3 HDPE PIPE PN -6: CLASS PE -100 90 0.34
4 HDPE PIPE PN -6: CLASS PE -100 110 0.11
5 HDPE PIPE PN -6: CLASS PE -100 125 0.93
6 HDPE PIPE PN -6: CLASS PE -100 140 0.10
7 HDPE PIPE PN -6: CLASS PE -100 160 0.03
8 HDPE PIPE PN -6: CLASS PE -100 180 138
HSC Connection
Sno. Total Nos.
Other Details
2.89
2.89
2.37
31-Dec-2025
01-Jan-2026