Project Completion Certificate (Ground Water)
Scheme ID: 20015513 Name of Scheme: shankarpur pitrihai wss No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 4130 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 24-Sep-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 24.18/96.37 SHANKARPUR PITRIHAI 27.95165 79.562839
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VP PUMP -1 52.56 M3 / 45 M SHANKARPUR PITRIHAI 27.95165 79.562839
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT -1 250 KL-16 M SHANKARPUR PITRIHAI 27.95195 79.562890
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 K-7 150 0.0295
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE / 6Kg 63 10.399
2 HDPE / 6Kg 75 0.445
3 HDPE / 6Kg 90 1.650
4 HDPE / 6Kg 110 2.660
5 HDPE / 6Kg 140 2.001
6 HDPE / 6Kg 160 0.415
7 HDPE / 6Kg 180 0.029
HSC Connection
Sno. Total Nos.
1 630
Other Details
3.28
0.00
3.26
24-Dec-2023
06-Dec-2024