| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20014690 | Name of Scheme: USMANPUR TUSUI | No. of Villages: 2 | No. of Habitation Covered: 2 |
| Total Population Covered: 2290 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 31-Dec-2024 | Actual Date of Completion (Capex): 27-Jul-2023 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 18/81.21 | USMANPUR TISUI | 27.952699 | 79.652327 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | VP PUMP -1 | 31.20 M3 / 47 M | USMANPUR TISUI | 27.952699 | 79.652327 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT -1 | 150 KL-16 M | USMANPUR TISUI | 27.952841 | 79.652442 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | K-7 | 100 | 0.029 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE / 6Kg | 63 | 3.863 | |
| 2 | HDPE / 6Kg | 75 | 0.070 | |
| 3 | HDPE / 6Kg | 90 | 0.255 | |
| 4 | HDPE / 6Kg | 110 | 1.354 | |
| 5 | HDPE / 6Kg | 140 | 1.295 | |
| 6 | HDPE / 6Kg | 160 | 0.150 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 398 |