Project Completion Certificate (Ground Water)
Scheme ID: 20012832 Name of Scheme: AKODIYA WATER SUPPLY SCHEME No. of Villages: 3 No. of Habitation Covered: 3
Total Population Covered: 3831 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 31-Jul-2025 Actual Date of Completion (Capex): 28-Nov-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TW 27/139.39 Akodiya 25.798615 81.887611
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible pump 39/54 Akodiya 25.798615 81.887611
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 200/16 Akodiya 25.798615 81.887611
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-9 125 0.0125
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 6.524
2 HDPE 75 0.9503
3 HDPE 90 0.6552
4 HDPE 140 3.1947
HSC Connection
Sno. Total Nos.
1 580
Other Details
2.26
0.00
2.06
20-Nov-2025
29-Nov-2025