| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20012223 | Name of Scheme: Jafarpur | No. of Villages: 2 | No. of Habitation Covered: 2 |
| Total Population Covered: 1560 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 26-Jul-2023 | Actual Date of Completion (Capex): 01-Oct-2023 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 12.02M/ 126.37M | Jafarpur | 27.527249 | 80.237232 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 0.2 M³ per Min /45Mtr | Jafarpur | 27.527249 | 80.237232 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 50 KL/ 14 Mtr | Jafarpur | 27.527437 | 80.232712 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | D. I. Pipe | 80 | 0.01886 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE Pipe PN-6, Class PE-100 | 63 | 1.519 | |
| 2 | HDPE Pipe PN-6, Class PE-100 | 75 | 0.708 | |
| 3 | HDPE Pipe PN-6, Class PE-100 | 90 | 1.483 | |
| 4 | HDPE Pipe PN-6, Class PE-100 | 110 | 0.140 | |
| 5 | HDPE Pipe PN-6, Class PE-100 | 125 | 0.185 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 250 |