| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20011119 | Name of Scheme: Phardahni | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 2580 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 02-Aug-2023 | Actual Date of Completion (Capex): 19-Dec-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 24.12/120.72 | Phardhani | 26.9539 | 83.2491 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible Pump | 36/40 | Phardhani | 26.9539 | 83.2491 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | Overhead Tank-1 | 175/12 | Phardhani | 26.9539 | 83.2491 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 100 | 0.035 | Laying Completed |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 5.847 | Laying Completed |
| 2 | HDPE | 75 | 0.236 | Laying Completed |
| 3 | HDPE | 90 | 0.939 | Laying Completed |
| 4 | HDPE | 110 | 0.604 | Laying Completed |
| 5 | HDPE | 140 | 0 | Laying Completed |
| 6 | HDPE | 160 | 0.269 | Laying Completed |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 400 |