| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20010953 | Name of Scheme: AJOSI | No. of Villages: 1 | No. of Habitation Covered: 11 |
| Total Population Covered: 3170 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2057 |
| Date of Completion (As per Contract): 22-May-2023 | Actual Date of Completion (Capex): 13-Oct-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tube well -300X150 | 30.13/191.51 | AJOSI | 25.695401 | 82.561175 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Pump-15HP | 650/47.90 | AJOSI | 25.695401 | 82.561175 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 200KL/14M | AJOSI | 25.695305 | 82.561243 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI K-9 | 150 | 0.0093 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE PIPE PN-6 | 160 | 0.496 | |
| 2 | HDPE PIPE PN-6 | 140 | 0.636 | |
| 3 | HDPE PIPE PN-6 | 110 | 1.260 | |
| 4 | HDPE PIPE PN-6 | 90 | 0.318 | |
| 5 | HDPE PIPE PN-6 | 75 | 0.267 | |
| 6 | HDPE PIPE PN-6 | 63 | 9.929 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 357 |