Project Completion Certificate (Ground Water)
Scheme ID: 20010953 Name of Scheme: AJOSI No. of Villages: 1 No. of Habitation Covered: 11
Total Population Covered: 3170 Base Year: 2022 Intermediate Year: 2037 Design Year: 2057
Date of Completion (As per Contract): 22-May-2023 Actual Date of Completion (Capex): 13-Oct-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube well -300X150 30.13/191.51 AJOSI 25.695401 82.561175
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Pump-15HP 650/47.90 AJOSI 25.695401 82.561175
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 200KL/14M AJOSI 25.695305 82.561243
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-9 150 0.0093
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN-6 160 0.496
2 HDPE PIPE PN-6 140 0.636
3 HDPE PIPE PN-6 110 1.260
4 HDPE PIPE PN-6 90 0.318
5 HDPE PIPE PN-6 75 0.267
6 HDPE PIPE PN-6 63 9.929
HSC Connection
Sno. Total Nos.
1 357
Other Details
2.53
2.36
2.18
13-Oct-2025
14-Oct-2025