Sr.No. District City/Town Name of Sewerage Project Scheeme Type Mode of Project AA&ES and date No. of STP STP Capacity No.Of Drains Agency Name Agreement Cost
Date of Start
Date of Comp. As per Agreement
Revised Date
Current Progress Component Wise Physical progress
Date of updation
Remark
Date of Sanction Sanction cost work Cost Centage O & M Cost Physical Progress(%) Financial Progress(Cr)
Work Component
No Of Component Capacity/Length/No Physical Progress(%) Photos
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Total -- -- -- 5883.27 2684.46 189.47 2997.22 38 1009.30 134 -- 4109.24 -- -- -- -- -- -- -- -- +0
38.55
-- --
1 Agra Agra Agra Sewerage Scheme( Interception & diversion and STP works) NGP2-EAP HAM 06-May-2020 842.25 371.29 25.40 445.56 13 177.60 26 M/s AWWMPL Pvt Ltd 582.84 05-Apr-2023 04-Apr-2025
04-Apr-2025
+0.45
51.14
+0.00
150.22
Effluent Disposal Line (km.) 2 2.01 +0
79.00
8 18-Nov-2024
  • Component wise progress of Agra (HAM) 100 MLD STP- 62.50%, WIP 35 MLD STP- 70%, WIP 31 MLD STP- 68%, WIP MPS 03 Nos.- 10%, WIP Rising Main 9.55 Km- 38.64%, WIP Gravity Sewer 2.55 Km- 80%, WIP DSTP 10 Nos.- 5%, WIP Note- 1st Stage permission is granted for 07 Nos. DSTP Forest Land and 2nd stage permission is under process
Intercepting Sewer (km) 3 1.94 +0
34.00
4
Interception And Diversion 1 22.00 +0
0.00
0
MPS (MLD) 3 373.50 +0
1112.67
40
Rising main (mtr.) 3 8.97 +0
62.67
9
STP (MLD) 13 177.60 +0
17.62
47
2 Mathura Chhata Chhata Town Sewerage Scheme (I&D and STP works), District Mathura NGP DBOT 25-Oct-2022 56.15 34.52 2.23 19.40 1 6.00 14 M/s Shailesh Kumar J.V. 48.97 12-Nov-2024 11-Aug-2026 +0.00
0.00
+0.00
0.00
Boundary wall 1 450.00 +0
0.00
0
  • Date of Start 12.11.2024 has been given to the firm. Survey and other related works is going on.
Admin Block 1 1.00 +0
0.00
0
Intercepting Sewer (km) 1 2.17 +0
0.00
0
MPS (MLD) 1 13.50 +0
0.00
0
Nala Tapping Arrangement ( No.) 1 11.00 +0
0.00
0
Rising main (mtr.) 1 5.50 +0
0.00
0
Staff Quarter type 2 1 1.00 +0
0.00
0
STP (MLD) 1 6.00 +0
0.00
0
3 Mathura Vrindavan I&D and 13 MLD STP works at Vrindavan City NGP DBOT 25-Oct-2022 77.70 39.90 2.56 35.24 1 13.00 2 M/s SIMA -G D- N.P. (JV) 65.86 11-Jun-2024 10-Mar-2026 +0.70
5.00
+0.00
0.00
Boundary wall (mtr.) 1 440.00 +0
85.00
0 18-Nov-2024
  • LOA issued to firm on dated 15.03.2024. Effective Date of start for the work is 11.06.2024.Work is in progress.
Intercepting Sewer (km) 1 0.60 +0
0.00
0
MPS (MLD) 1 29.25 +0
0.00
0
Nala Tapping Arrangement ( No.) 1 2.00 +0
0.00
0
No of Drains-05 nos 1 2.00 +0
0.00
0
Rising main (mtr.) 1 3.70 +0
0.00
0
STP (MLD) 1 13.00 +0
6.00
4
Upgradation of MPS 1 7.00 +0
0.00
0
4 Shamli Banat I&D and STP Work in Banat, Shamli NGP DBOT 25-May-2023 48.71 24.93 1.58 22.20 1 5.00 3 M/s R K Engineers Sales Ltd 37.92 14-Oct-2024 13-Jan-2026 +0.00
0.00
+0.00
0.00
Co-treatment Unit for Fecal Sludge (KLD) 1 5.00 +0
0.00
0 20-Nov-2024
  • LOA issue to M/s R.K. Engineers Sales Ltd. on Date 13-09-2024
  • Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
Effluent Disposal Line (km.) 1 0.60 +0
0.00
0
Interception And Diversion 1 2.00 +0
0.00
0
MPS (MLD) 1 5.00 +0
0.00
0
Power Connection 1 1.00 +0
0.00
0
Rising main (mtr.) 1 0.04 +0
0.00
0
Sewer Line (km.) 1 0.60 +0
0.00
0
STP (MLD) 1 5.00 +0
0.00
0
5 Shamli Bantikhera Banat I&D and STP Work in Bantikhera and Babri village, Shamli NGP DBOT 25-May-2023 55.47 29.41 1.84 24.22 1 5.00 1 M/s R K Engineers Sales Ltd 41.91 14-Oct-2024 13-Jan-2026 +0.00
0.00
+0.00
0.00
Effluent Disposal Line (km.) 1 0.40 +0
0.00
0 20-Nov-2024
  • LOA issue to M/s R.K. Engineers Sales Ltd. on Date 13-09-2024
  • Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
Interception And Diversion 1 4.00 +0
0.00
0
MPS (MLD) 1 6.00 +0
0.00
0
Power Connection 1 1.00 +0
0.00
0
Rising main (mtr.) 1 0.04 +0
0.00
0
Sewer Line (km.) 1 2.00 +0
0.00
0
STP (MLD) 1 5.00 +0
0.00
0
6 Muzaffarnagar Muzzaffarnagar I&D and STP Work in Muzaffarnagar NGP HAM 13-Jan-2020 234.03 108.32 7.33 118.36 2 54.50 5 M/S Muzaffarnagar STP Pvt Ltd 205.09 04-Jun-2021 03-Jun-2023
30-Jun-2024
30-Sep-2024
+0.00
95.68
+0.00
141.79
Co-treatment Unit for Fecal Sludge (KLD) 2 100.00 +0
100.00
12 20-Nov-2024
  • 22 MLD STP Sahawali: Commissioned on 07.06.2023. Project completed on Oct, 2023
  • 32.5 MLD Kidwai Nagar: 02 Nos. I&D work completed, STP commissioned by Manual Mode by 02 I&D on dated 18 February, 2024. IPS 2A work in progress.
Effluent Disposal Line (km.) 1 0.80 +0
99.60
15
Interception And Diversion 1 5.00 +0
85.20
12
IPS (MLD) 1 8.36 +0
95.00
8
MPS (MLD) 1 27.00 +0
95.00
8
Power Connection 1 2.00 +0
100.00
8
Rising main (mtr.) 1 2.40 +0
99.70
24
Sewer Line (km.) 1 1.48 +0
100.00
0
SPS (MLD) 2A 1 20.00 +0
88.90
15
STP (MLD) 2 54.50 +0
97.30
41
7 Shamli Shamli I&D and STP Work in Shamli NGP DBOT 25-May-2023 206.02 103.19 6.66 96.17 1 40.00 1 M/s R.K. Engineers Sales Ltd.-M/s Anand Constrwell Pvt. Ldt. (JV) 120.92 14-Oct-2024 13-Jan-2026 +0.00
0.00
+0.00
0.00
Co-treatment Unit for Fecal Sludge (KLD) 1 20.00 +0
0.00
0 20-Nov-2024
  • LOA issue to M/s R.K. Engineers Sales Ltd.-M/s Anand Constrwell Pvt. Ldt. (JV) on Date 04-07-2024
  • Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
Effluent Disposal Line (km.) 1 0.10 +0
0.00
0
Interception And Diversion 1 1.00 +0
0.00
0
MPS (MLD) 1 40.00 +0
0.00
0
Power Connection 1 1.00 +0
0.00
0
Rising main (mtr.) 1 0.10 +0
0.00
0
Sewer Line (km.) 1 0.10 +0
0.00
0
STP (MLD) 1 40.00 +0
0.00
0
8 Shamli Thanabhawan I&D and STP Work in Thanabhawan, Shamli NGP DBOT 25-May-2023 97.19 55.63 3.50 38.06 1 10.00 5 M/s R K Engineers Sales Ltd 63.72 14-Oct-2024 13-Jan-2026 +0.00
0.00
+0.00
0.00
Co-treatment Unit for Fecal Sludge (KLD) 1 10.00 +0
0.00
0 20-Nov-2024
  • LOA issue to M/s R.K. Engineers Sales Ltd. on Date 31-08-2024
  • Contract Agreement is signed on 08.10.2024 and Date of Start 14-10-2024 & Date of Completion 13-01-2026
Interception And Diversion 1 3.00 +0
0.00
0
MPS (MLD) 1 10.00 +0
0.00
0
Power Connection 1 1.00 +0
0.00
0
Rising main (mtr.) 1 0.04 +0
0.00
0
Sewer Line (km.) 1 5600.00 +0
0.00
0
STP (MLD) 1 10.00 +0
0.00
0
9 Hapur Hapur I&D and STP works at District-Hapur NGP DBOT 19-Sep-2023 49.06 22.85 1.42 24.79 1 6.00 1 M/s SKC Technocrat Pvt. Ltd (Formerly M/s Satish Kumar & Co.) & M/s. Geo Miller & Co. Pvt. Ltd. (JV) 39.28 08-Nov-2024 07-Nov-2026 +0.00
0.00
+0.00
0.00
Drains 1 1.00 +0
0.00
0
  • Financial bid evaluation report sent to NMCG 0n 12.08.24
  • NOC received from NMCG New Delhi for Financial Bid on Dated 20-08-2024 vide letter no Pr-14011/04/2018-Tech Construction NMCG Dated 20.08.2024
  • LOI issued to M/s Satish Kumar vide SE Lt No. 196/790/10 Dt 24.08.24
  • Bank Guarantee not submitted by Firm.
  • Date of start is given on 08.11.24. Date of completion of work is 05.02.2026 to M/s SKC Technocrat Pvt. Ltd (Formerly M/s Satish Kumar & Co.) & M/s. Geo Miller & Co. Pvt. Ltd. (JV), Reg. Office B-29, IIIrd Floor, RDC Rajnagar, Ghaziabad - 201013. AGREEMENT cost of project is Rs. 39,28,13,617.00.
MPS (MLD) 1 8.00 +0
0.00
0
STP (MLD) 1 6.00 +0
0.00
0
10 Farrukhabad Farrukhabad-Fatehgarh I&D and STP works at Farrukhabad-Fatehgarh NGP HAM 09-Feb-2021 261.12 188.71 6.98 72.41 2 47.70 8 M/S HNB Engineers Private Ltd. 252.41 28-Jun-2022 27-Jun-2024
27-Jun-2024
30-Sep-2024
31-Aug-2024
31-Oct-2024
+0.10
95.60
+0.00
179.04
Intercepting Sewer (km) 1 5.10 +0
95.60
5 18-Nov-2024
  • Construction of STP has been completed. Electrical and Mechanical works of STP and associated I and D works are in progress. The power connection is to be provided by concerning department UPPCL. The power connection work under progress.
Interception And Diversion 1 4.00 +0
95.60
4
MPS (MLD) 1 30.00 +0
95.60
5
Rehabilitation of SPS/MPS 1 2.00 +0
95.60
11
Rising main (mtr.) 1 2.50 +0
95.60
4
SPS (MLD) 2A 1 1.00 +0
95.60
4
STP (MLD) 2 47.70 +0
95.60
21
11 Hathras Hathras I&D and STP works at Hathras Town NGP DBOT 30-Jan-2023 128.91 70.48 4.55 53.88 1 24.00 10 M/s Neercare India pvt KLtd JV M/s EMIT Group India Pvt Ltd JV EMS Ltd 119.05 05-Jun-2026 06-Sep-2024
05-Jun-2026
+0.00
0.00
+0.00
0.00
Admin Block 1 1.00 +0
0.00
0 15-Oct-2024
  • Date of start is 06.09.2024 and date of completion is 05.06.2024. Survey work is going on.
Boundary wall (mtr.) 1 800.00 +0
0.00
0
Intercepting Sewer (km) 1 5.67 +0
0.00
0
MPS (MLD) 1 54.00 +0
0.00
0
Nala Tapping Arrangement ( No.) 1 8.00 +0
0.00
0
Rising main (mtr.) 1 0.13 +0
0.00
0
Staff Quarter type 2 1 1.00 +0
0.00
0
STP (MLD) 1 24.00 +0
0.00
0
12 Kanpur Nagar Kanpur Nagar I&D and STP works at Kanpur-Pankha NGP HAM 12-Mar-2018 967.23 248.39 31.05 718.84 1 30.00 2 M/s Kanpur River Management Pvt. Ltd. 708.70 11-Oct-2019 25-Oct-2021
29-Feb-2024
30-Sep-2024
31-Aug-2024
31-Oct-2024
+0.00
99.00
+0.00
298.00
MPS (MLD) 1 115.00 +0
99.00
12 18-Nov-2024
  • 30 MLD Panka STP has been commissioned. Works of Sludge handling Unit has been completed. OCEMS has been installed but not functional.
O & M 3 295.00 +0
99.00
18
Sewer Line (km.) 1 16.00 +0
99.00
8
SPS (MLD) 2A 2 45.00 +0
99.00
18
STP (MLD) 1 30.00 +0
99.00
8
Upgradation of STP 1 130.00 +0
99.00
8
13 Mathura Kosi Kalan I&D and STP works at Kosi Kalan Town, District Mathura NGP DBOT 25-Oct-2022 66.59 31.24 2.03 33.32 1 12.00 1 M/s R K Engineers Sales Ltd 53.60 16-Oct-2024 15-Jul-2026 +0.00
0.00
+0.00
0.00
Admin Block 1 1.00 +0
0.00
0
  • LOA has been issued on date 18.06.2024 and Date of start has been given 16.10.2024 to the firm. Survey work is going on
Boundary wall (mtr.) 1 500.00 +0
0.00
0
Intercepting Sewer (km) 1 0.03 +0
0.00
0
MPS (MLD) 1 27.00 +0
0.00
0
Nala Tapping Arrangement ( No.) 1 1.00 +0
0.00
0
Rising main (mtr.) 1 0.10 +0
0.00
0
Staff Quarter type 2 1 1.00 +0
0.00
0
STP (MLD) 1 12.00 +0
0.00
0
14 Meerut Meerut I&D and STP works at Meerut NGP2-EAP HAM 06-May-2020 690.71 363.78 26.31 280.19 1 220.00 2 M/s. Meerut STP Pvt. Ltd. 369.74 11-Nov-2024 10-Nov-2026 +0.00
0.00
+0.00
0.00
Interception And Diversion 1 2.00 +0
0.00
0
  • Financial closure document and condition precedends is submitted to NMCG on dt 23.09.2024
  • Date of Start 11-11-2024 & Date of Completion 10-11-2026
  • Agreement is signed on 05.09.2023, Financial closure document is sent to NMCG on 15.05.2024 for review.
  • Due to non fulfillment of predefined condition precedends letter issued to concessanaire on dated 05.06.2024, 18.06.2024 and 30.07.2024.
  • LoA issued to JV M/s GA Infra ltd. Rajasthan and M/s SSG Infratech Pvt. Ltd, New Delhi on 27.05.2023.
MPS 1 1.00 +0
0.00
0
Power Connection 1 1.00 +0
0.00
0
Rising main (mtr.) 1 0.10 +0
0.00
0
Sewer Line (km.) 1 0.56 +0
0.00
0
STP (MLD) 1 220.00 +0
0.00
0
15 Varanasi Varanasi I&D and Treatment works for Assi-BHU Area (Phase-II), Varanasi NGP DBOT 19-Oct-2022 308.09 97.62 7.81 172.94 1 55.00 2 M/s Enviro Infra Engineers limited MTS JV 151.55 07-Mar-2024 06-Dec-2025 +1.00
21.00
+11.18
19.82
Co-Treatment Facility(KLD) 1 10.00 +0
0.00
0 20-Nov-2024
  • BEP submitted by firm to which observation have been raised. compliance pending.
  • Soil testing done. Team mobilized at site.
  • Meeting held under chairmanship of APD Sir on 20.06.2024 to resolve issues of design/drawing. Firm submitted BEP of STP only on 24.06.2024
  • Vetting of process flow of STP and MPS done by IIT-BHU. Structural drawing awaited. Preparatory works in progress
Effluent Disposal Line (km.) 1 1.32 +0
5.00
5
IPS (MLD) 1 6.00 +0
3.00
12
MPS (MLD) 1 50.00 +0
11.00
10
Nala Tapping Arrangement ( No.) 1 2.00 +0
3.00
0
Rising main (mtr.) 1 2.10 +0
27.00
4
STP (MLD) 1 55.00 +0
23.00
11
16 Unnao Shuklaganj I&D of Drains and STP works in Shuklaganj (05MLD) NGP HAM 28-Jul-2017 65.18 25.93 1.90 37.35 1 5.00 5 M/s KRMPL Kanpur 38.87 11-Oct-2019 10-Jul-2021
10-Jul-2021
13-Jun-2023
14-Dec-2022
31-Aug-2024
31-Jan-2025
+0.00
81.00
+0.00
23.47
Boundary wall, staff quarter 1 526.00 +0
78.00
4 18-Nov-2024
  • There are only 10-20 manpower has been engaged in centrifuge. Manhole PTU and I&D work No any manpower deployed in Electrical & Mechanical works from last 8-10 months. Progress of work is very poor.
Connecting Sewer 450mm 1 50.00 +0
95.00
4
Effluent Channel 1 100.00 +0
30.00
4
Interception & Diversion of Indra Nagar Drain (Nal 1 1.00 +0
85.00
8
MPS (8M dia, 20 MLD) 1 1.00 +0
85.00
4
Online Monitoring System for STP (1 inlet+1 outlet 1 2.00 +0
0.00
0
Rising Main (1000mm dia DI K9) 1 100.00 +0
93.00
4
STP (MLD) 1 5.00 +0
85.00
4
17 Unnao Unnao I&D of Drains and STP works in Unnao (15MLD) NGP HAM 28-Jul-2017 102.20 43.73 3.22 55.25 1 15.00 1 M/s KRMPL Kanpur 68.68 11-Oct-2019 10-Jul-2021
10-Jul-2021
15-Mar-2023
15-Oct-2022
15-Sep-2021
25-Feb-2022
30-Apr-2023
30-Jun-2024
31-Dec-2024
31-Jul-2024
+0.00
95.50
+0.00
52.01
Boundary wall, staff quarter 1 1.00 +0
90.00
16 18-Nov-2024
  • Cleaning of 423mt. sewer line is balance till date and From last 2-3month KRMPL not deployed manpower at site for cleaning of Sewer line. STP 4-6 Hrs operating daily from 07.11.2023 through temporary line.
Connecting Sewer 1100mm 1 3.20 +0
90.00
12
Effluent Channel 1 300.00 +0
95.00
8
Extra Item : Laying of 1200mm dia gravity sewer li 1 230.00 +0
100.00
8
Interception & Diversion of City Jail Drain (Nala 1 1.00 +0
95.00
9
MPS (15M dia 40MLD) 1 1.00 +0
97.00
8
Online Monitoring System for STP (1 inlet+1 outlet 1 1.00 +0
60.00
10
Rising Main (750mm dia) 1 100.00 +0
95.00
8
STP (MLD) 1 15.00 +0
96.00
9
18 Moradabad Moradabad Interception & Diversion (I&D) of Drains and Sewerage Treatment Plant at Moradabad zone 2 NGP HAM 23-Jul-2018 118.69 53.53 3.52 61.64 1 25.00 5 Moradabad STP Pvt Ltd 113.85 20-Jan-2023 19-Jan-2025
19-Jan-2025
+0.50
81.00
+0.00
54.19
Boundary wall 1 1.00 +0
80.00
4 18-Nov-2024
  • SBR progress is 85% and sewer has been laid 4669 m out of 6632
  • 03 milestones have been completed and 81% progress is achieved of project
Interception And Diversion 1 4.00 +0
40.00
4
MPS (MLD) 1 40.00 +0
80.00
12
Rising main (mtr.) 1 50.00 +0
0.00
0
Sewer Line (km.) 1 6.64 +0
78.00
9
STP (MLD) 1 25.00 +0
85.00
18
19 PrayagRaj Prayagraj Interception, Diversion of Balance 13 drains and Augmentation of Salori STP capacity by 43 MLD (Sewerage District-C) at Prayagraj Uttar Pradesh under DBOT mode NGP DBOT 14-Mar-2023 331.75 180.27 11.22 140.27 1 43.00 13 M/s HNB Private ltd. - M/s Tirupati Cements Products (JV) 204.40 19-Mar-2024 18-Aug-2025 +1.32
30.12
+0.00
22.74
3 MLD Sitaram Ghat SPS 1 3.00 +0
0.00
0 20-Nov-2024
  • Basic Engineering Package has been vetted by IIT Delhi and same approved by UPJN (R)
  • GAD & RCC Design and Drawings of CCT, SBR Unit and Amitabh Bachhan Culvert SPS has been vetted by IIT Delhi and approved by UPJN (R)
  • Piling work is under progress for Primary Treatment Unit & Air Blower Room
  • RCC work for Raft and wall of SBR unit Basin 2, 3 & 4 of STP is under progress. PCC of Basin 1 has been completed and reinforcement work is under progress.
  • Casting of Outer Wall is completed .baffle wall work is under progress.
  • Casting of 3rd Lift of Wall at AB Culvert SPS has been completed. Sinking work up to 3rd Lift Completed. Reinforcement work is under progress
  • 2050 m laying of Rising main completed. Balance Laying is under progress
  • TEPS excavation & PCC work Completed and Reinforcement work is under progress.
32 MLD AB Culvert SPS 1 32.00 +0
0.00
2
Effluent Disposal Line (km.) 1 0.30 +0
0.00
0
Effluent Pumping Station (MLD) 1 43.00 +0
0.00
0
Interception And Diversion 1 13.00 +0
0.00
0
Rehabilitation of Sewer Line 1 3.30 +0
0.00
0
Rising main (mtr.) 1 4070.00 +0
0.00
8
Sewer Line (km.) 1 2.16 +0
0.00
4
STP (MLD) 1 43.00 +0
0.00
20
20 PrayagRaj Prayagraj Interception, Diversion of Balance 7 drains and Augmentation of Rajapur STP capacity by 90 MLD (Sewerage District-D) at Prayagraj Uttar Pradesh under DBOT mode NGP DBOT 27-Jan-2023 475.98 242.85 15.24 217.89 1 90.00 7 M/s Triveni Engineering and Industries 309.74 24-Aug-2024 23-Feb-2026 +1.00
4.00
+0.00
7.12
Effluent Disposal Line (km.) 1 0.30 +0
0.00
0 20-Nov-2024
  • NMCG, New Delhi has given consent on dated 02.08.2024 regarding approval of financial bid.
  • Letter of Award (LOA) has been issued to the firm on dated 09.08.2024
  • Contract Agreement has been executed.
  • Date of Start 24.08.2024 and Date of Completion 23.02.2026 including 3 month of Trial and run has been given to the firm M/s Triveni Engineering and Industries Limited.
  • Survey, Design and Drawing work is in progress
  • Supply of 1000 DI K-9 Pipe for rising main is in progress.
  • Laying of rising main (1000 DI K-9 Pipe) is in progress
Effluent Pumping Station (MLD) 1 90.00 +0
0.00
0
Interception And Diversion 1 7.00 +0
0.00
0
Rehabilitation of Bund and Bund Road 1 1.00 +0
0.00
0
Rising main (mtr.) 1 3.45 +0
0.00
4
Sewer Line (km.) 1 4.20 +0
0.00
0
SPS (MLD) 2A 2 95.00 +0
0.00
0
STP (MLD) 1 90.00 +0
0.00
0
21 Lucknow Lucknow Pollution Abatement Of Gomti River (Phase 1 Part 1) Lucknow NGP DBOT 06-May-2020 213.91 101.31 6.97 105.63 2 42.50 2 M/s R.K. Engineers- Khilari Infrastructure (JV) 174.93 01-Jun-2022 30-Nov-2023
31-Jul-2024
31-May-2024
+0.00
96.63
+0.00
94.86
STP (MLD) 2 42.50 +0
47.97
14 18-Nov-2024
  • 39 MLD STP construction work completed and Trial & Run is in progress.
  • Date of start of 3.5 MLD Barikala STP is given on dt. 07.09.2024 to M/s R.K. Engineers Sales Ltd. - Khilari Infrastructures (JV). Presently STP site is submerged due to rain water. Presently Dewatering work is in progress.
Uppgradation of SPS 3 3.00 +0
100.00
0
22 Lucknow Lucknow Pollution Abatement of Gomti River (Phase-II, Part-I) Lucknow NGP DBOT 30-Jan-2023 264.67 137.55 8.53 118.60 1 50.00 3 M/s R.K. Engineers- Khilari Infrastructure (JV) 187.74 14-Jun-2024 13-Dec-2025 +0.00
0.00
+0.00
0.00
Interception And Diversion 1 3.00 +0
0.00
0 18-Nov-2024
  • Date of start is given on date 14.06.2024 to M/s R.K. Engineer sales ltd.-Khliari Infrastructures (JV). Construction of Staff Quarter is in progress. BEP for STP is submitted on dt. 12.11.2024, while site of SPS is submerged with rain water and dewatering work is in progress.
Rising main (mtr.) 1 3.50 +0
0.00
0
SPS (MLD) 1 22.60 +0
0.00
0
STP (MLD) 1 50.00 +0
0.00
0
23 Ayodhya Faizabad Pollution Abatement Works for River Saryu/Ghaghara at Faizabad town, District-Ayodhya (Interception & Diversion of Drains with 33 MLD STP) NGP HAM 06-May-2021 221.66 109.03 7.62 105.01 1 33.00 15 M/s Eco Protection Engineer Pvt Ltd 149.47 03-Mar-2023 02-Jan-2025
30-Sep-2024
31-Dec-2024
31-May-2024
+0.04
96.02
+0.00
76.75
Boundary wall (mtr.) 1 200.00 +0
97.55
4 20-Nov-2024
  • NMCG has given NOC for discharge of treated effluent in Saryu River dated 19.08.2024. Subsequently, correspondence with all supporting documents has been given to Irrigation Department for NOC of crossing effluent line across Bundha.
  • Precommissioning of MPS, PTU, SBR basin, Diffuser, Blower, Disc filter has been completed.
Effluent Disposal Line (km.) 1 0.06 +0
65.00
4
MPS (MLD) 1 41.60 +0
98.88
4
Rising main (mtr.) 1 0.40 +0
99.00
4
Sewer Line (km.) 1 3.88 +0
97.88
5
STP (MLD) 1 33.00 +0
98.01
4

© Copyright 2020 Jal Jeevan Mission - Uttar Pradesh | Design & Developed By SigmaIT Software Designers Pvt. Ltd