| 1 |
8153338 |
Dhauha GOV |
ESR 12 |
Mirzapur |
Rajgarh |
Ban Imiliya |
Ban Imiliya |
Road Widening[PWD] |
08-Jan-2026 |
31-Aug-2026 |
Pipeline laying work is already in progress, due to which water supply to 7 habitations has been affected and is currently interrupted |
| 2 |
8153338 |
Dhauha GOV |
ESR 14 |
Mirzapur |
Rajgarh |
Rampur Sakteshgarh |
Rampur Sakteshgarh |
Road Widening[PWD] |
08-Jan-2026 |
31-Aug-2026 |
Pipeline laying work is already in progress, due to which water supply to 3 habitations has been affected and is currently interrupted |
| 3 |
8153338 |
Dhauha GOV |
ESR 14 |
Mirzapur |
Rajgarh |
Kothilawa |
Kothilawa |
Road Widening[PWD] |
|
|
The pipeline was damaged by the PWD during the road widening work. |
| 4 |
8153338 |
Dhauha GOV |
ESR 9 |
Mirzapur |
Rajgarh |
Siriya |
Chakjata |
Local Repairing |
|
|
Pipeline Repair Work is Currently Under Progress. |
| 5 |
8153338 |
Dhauha GOV |
ESR 25 |
Mirzapur |
Narainpur |
Lijhri Kala |
Majhiyar |
Damage Village Internal Works |
|
10-Aug-2026 |
Pipeline was damaged during village road construction. Repair work is currently in progress. |