1 |
Jajmau CETP |
350 |
36 |
UPJN(Urban) |
Non Compliant |
20 MLD new CETP is under construction |
2 |
Rooma Apparel Park |
11 |
1.5 |
RPCC (SPV) |
Compliant |
Plant is designed under capacity. Upgradation needed |
3 |
Banther CETP |
42 |
4.5 |
BIPCC (SPV) |
Non Compliant |
Upgradation is Ongoing though Namami Gange Programme |
4 |
Unnao CETP |
15 |
2.15 |
UTPCC( SPV) |
Non Compliant |
LOA issued. Agreement to be signed |
5 |
Mathura CETP |
17 |
6.25 |
MACPNL(SPV) |
Compliant |
Upgraded done through Namami Gange Programme |
6 |
Tronica City |
470 |
6 |
Tronica City SPV |
Compliant |
As per directions from NMCG the cetp is allowed to operate at 50 % capacity. UPSIDA have to upgrade the plant |
7 |
HPDA, Pilkuwa |
15 |
2.1 |
HPDA SPV |
Compliant |
Upgradation Completed by HPDA |
8 |
Bhadohi CETP |
30 |
1 MLD |
BIDA |
Defunct |
Plant declared obselete |
9 |
Moradabad |
63 |
2.4 |
UPSIDA |
Defunct |
Plant is in a Obselete state |