Sr.No. Name of Sewerage Project Scheeme Type Mode of Project AA&ES and date No. of STP STP Capacity No.Of Drains Agency Name Agreement Cost Date of Comp. As per Agreement Date of Start Expected Date of Completion. Previus progress Current progress Weekly progress Critical Issu Remark
Date of Sanction Sanction cost work Cost Centage O & M Cost Physical Progress Financial Progress Physical Progress Financial Progress Physical Progress Financial Progress(CR)
Total -- 3615.90 1518.98 115.03 2015.06 32 543.30 154 -- 2981.94 -- -- -- 1139.47 1170.07 1146.58 1245.58 7.11 75.51 -- --
1 Agra Sewerage Scheme( Interception & diversion and STP works) NGP2-EAP HAM 06-May-2020 842.25 371.29 25.40 445.56 13 177.60 26 M/s AWWMPL Pvt Ltd 582.84 04-Apr-2025 05-Apr-2023 04-Apr-2025 23.00 50.20 25.00 50.20 2.00 0.00 work in progress
2 Development of Sewage Treatment Plant at Bareilly NGP HAM 03-Jan-2019 271.39 139.44 10.70 121.25 3 63.00 15 M/s EIEPL Bareilly Infra Engineers Ltd 233.72 30-Aug-2024 31-Aug-2022 30-Aug-2024 86.50 181.03 86.50 181.03 0.00 0.00 20 mld and 1 mld STP is proposed to be commissioned before 15th Jan 2024.
3 I&D and STP Work in Budhana Town Non EAP HAM 18-Feb-2019 48.76 25.10 1.70 21.96 1 10.00 3 M/S Muzaffarnagar STP Pvt Ltd 41.28 03-Jun-2023 04-Jun-2021 31-Oct-2023 99.59 29.15 99.67 29.15 0.08 0.00 All 03 I&D and 10 MLD STP work completed. STP commissioned on 27.06.2023, Internal Road Construction, Land scaping etc. work in progress.
4 I&D and STP Work in Kairana NGP DBOT 07-Dec-2020 78.42 37.28 2.63 38.51 1 15.00 1 M/s SIPL RKC JV 59.19 27-May-2023 28-Aug-2021 31-Dec-2023 82.54 18.62 82.90 18.62 0.36 0.00 I&D work completed, STP Civil work almost completed, Electrical/Mechanical instrument procurement and installation work in progress.
5 I&D and STP Work in Muzaffarnagar NGP HAM 02-Jan-2019 78.42 37.28 2.63 38.51 2 54.50 5 M/S Muzaffarnagar STP Pvt Ltd 205.09 03-Jun-2023 04-Jun-2021 31-Dec-2023 89.59 141.79 89.68 141.79 0.09 0.00 22 MLD STP Sahawali: Commissioned on 07.06.2023. 32.5 MLD Kidwai Nagar: 02 Nos. I&D work completed, STP civil work 95% completed, E&M Instrument installation work in progress.
6 I&D and STP works at Farrukhabad-Fatehgarh NGP HAM 09-Feb-2021 261.12 188.71 6.98 72.41 2 47.70 8 M/S HNB Engineers Private Ltd. 252.41 27-Jun-2024 28-Jun-2023 27-Jun-2024 76.50 124.28 76.50 179.04 0.00 54.76
7 I&D and STP works at Kanpur-Pankha NGP HAM 12-Mar-2018 967.23 248.39 31.05 718.84 1 30.00 2 M/s Kanpur River Management Pvt. Ltd. 708.70 25-Oct-2021 11-Oct-2019 31-Oct-2023 98.00 258.27 98.00 258.27 0.00 0.00 30 MLD Panka STP has been commissioned. Rehabilitations work of Jajmau STP is under Progress.
8 I&D of Drains and Sewerage Treatment Plant works with 15 Years O&M at Sultanpur NGP DBOT 24-Dec-2018 64.76 36.50 2.59 23.91 2 7.00 4 M/s EIEPL- ABI(JV) 60.41 29-May-2022 30-Nov-2019 30-Sep-2023 99.75 44.04 99.75 44.04 0.00 0.00 Trail and Run of 10 MLD STP (Vinobapuri) ,5 MLD STP (Palhipur) & 02 MLD STP(Karaudiya) has been started
9 I&D of Drains and STP works in Shuklaganj (05MLD) NGP HAM 28-Jul-2017 65.18 25.93 1.90 37.35 0 0.00 5 M/s KRMPL Kanpur 38.87 10-Jul-2021 11-Oct-2019 31-Dec-2023 78.00 23.47 78.00 23.47 0.00 0.00 No any manpower has been engaged in civil & electrical mechanical works from last 4 months. The work of mechanical has started in sludge thickner and MPS, but in present no progress is getting as per
10 I&D of Drains and STP works in Unnao (15MLD) NGP HAM 28-Jul-2017 102.20 43.73 3.22 55.25 0 0.00 1 M/s KRMPL Kanpur 68.68 10-Jul-2021 11-Oct-2019 31-Oct-2023 95.50 52.01 95.50 52.01 0.00 0.00 Cleaning of 700 mt. sewer line is balance till date and no manpower has been deployed from last 3 months. Trial run of the Plant has been started after laying temporary sewer line from 07.11.2023 .
11 Interception & Diversion (I&D) of Drains and Sewerage Treatment Plant at Moradabad zone 2 NGP HAM 23-Jul-2018 118.69 53.53 3.52 61.64 1 25.00 5 Moradabad STP Pvt Ltd 113.85 19-Jan-2025 20-Jan-2023 19-Jan-2025 30.00 10.46 30.50 10.46 0.50 0.00
12 Interception & Diversion and STP at Mirzapur, U.P. NGP HAM 28-May-2020 129.08 50.50 4.04 73.06 2 17.00 18 M/s Mirzapur Ghazipur STPs Private Limited 151.58 09-Jan-2024 10-Apr-2022 09-Jan-2024 79.00 53.61 79.00 74.36 0.00 20.75 Rehabilitation of 14 MLD UASB STP completed.
13 Pollution Abatement Of Gomti River (Phase 1 Part 1) Lucknow NGP DBOT 06-May-2020 213.91 101.31 6.97 105.63 2 42.50 4 M/s R.K. Engineers- Khilari Infrastructure (JV) 174.91 30-Nov-2023 01-Jun-2022 30-Nov-2023 60.74 56.72 62.05 56.72 1.31 0.00 39 MLD DAULATGANJ STP WORK IN PROGRESS , 3.5 MLD BARIKALA STP FINANCIAL APPROVAL AWAITED FROM NMCG
14 Pollution Abatement Works for River Saryu/Ghaghara at Faizabad town, District-Ayodhya (Interception & Diversion of Drains with 33 MLD STP) NGP HAM 06-May-2021 221.66 109.03 7.62 105.01 1 33.00 15 M/s Eco Protection Engineer Pvt Ltd 149.47 02-Jan-2025 03-Mar-2023 31-Mar-2024 57.76 58.68 60.53 58.68 2.77 0.00
15 Sewerage, Sewage Treatment & Disposal for Ghazipur, U.P. NGP HAM 06-May-2020 152.83 50.96 4.08 96.17 1 21.00 42 M/s Mirzapur Ghazipur STPs Private Limited 140.94 09-Jan-2024 10-Apr-2022 09-Jan-2024 83.00 67.74 83.00 67.74 0.00 0.00 Proposal for additional cost implication is to be approved by NMCG