Under Construction CETP in Uttar Pradesh Under Namami Gange Programme

S No Project Name Executive Agency  Contractor / Firm Name Date of Sanction Date of Completion Sanction cost(Cr) Agreement Cost(Cr) Financial Progress Physical Progress Remarks
1 2 3 4 5 6 7 8 9 10 11
1 Jajmau 20MLD CETP JTETA Va Tech Wabag 7/24/2018 12:00:00 AM 617 520.14 314.0000 81.0000 Construction for 10 MLD treatment capacity is Complete. Trial run to start in next two weeks.
2 Banther CETP BIPCC (SPV) M/S EMS Infracon 2/21/2020 12:00:00 AM 108.96 111.96 16.5900 31.0000 Under Progress
3 MATHURA CETP MACPNL M/s Fateh Enviro Engineers 11/28/2018 12:00:00 AM 13.97 12.69 12.6900 100.0000 Post Construction trial run complete. Plant is under o&m
4 Jajmau 20MLD CETP JTETA Va Tech Wabag 7/24/2018 12:00:00 AM 617 520.14 314.0000 85.0000 Construction for 10 MLD treatment capacity is Complete. Trial run to start in next two weeks.
5 Banther CETP BIPCC (SPV) M/S EMS Infracon 2/21/2020 12:00:00 AM 108.96 111.96 16.5900 33.0000 Under Progress